A Bridge for Hungerford

Update November 2010

Since the last public meeting in Hungerford Corn Exchange of April 2010, the proposed Hungerford Canal Footbridge has taken several steps toward becoming reality.

The bridge engineers have continued their work to take the conceptual designs presented at the public meetings and transform them into detailed designs, in order to fulfill the planning process and have the bridge manufactured.

In September, residents of Hungerford may have seen the arrival of a team of geotechnical engineers who spent three weeks working in the wharf area to survey the ground conditions in precise detail. Trial holes were dug to investigate the existing bridge foundations and deep boreholes were drilled to examine the type and quality of the soil and rock. The laboratory tests and report will provide crucial information to allow the bridge engineer to design appropriate foundations for the bridge piers and north abutment.

As the footbridge design progressed, further consultation was undertaken with English Heritage and British Waterways in preparation for the planning submission in September 2010. A response from the West Berkshire Council Planners is expected by mid-November 2010. In anticipation of planning permission being granted, West Berkshire Council is preparing a list of suitable contractors who will be invited to tender for the construction and installation of the footbridge at the appropriate time. The tender process usually takes up to a month after which the most competitive and suitable contractor will be awarded the works.

The footbridge is designed in steel with a timber deck. The steelwork for the bridge will be fabricated in a factory and transported to site in several sections. The sections will then be craned and fixed into position on location in the wharf. Owing to the complex three-dimensional curves to which the bridge is designed, initial estimates for fabrication of the bridge are thought to be about five months. During the fabrication process, the contractor will begin work on site to install the foundations and prepare for the arrival of the bridge.

An important part of the scheme is to improve the approaches to the newly installed footbridge. The improvements will comprise widening the southern approach footpath from the High Street and some realignment where the footpath divides between crossing the canal and descending into the wharf. In order to widen the footpath, it is proposed to install new approach fences to the outside of the existing bridge wing walls. The fences will be designed to match the parapets on the new footbridge.

The completion date for the new footbridge is expected to be early summer 2011.

For further information, please visit www.westberks.gov.uk/hungerfordfootbridge

Back to the Top